Exit 14 ramps to remain closed up to 90 days for reconstruction
FRANKFORT, Ky. (July 3, 2023) – A contractor for the Kentucky Transportation Cabinet (KYTC) plans an extended closure of all ramps at the Julian Carroll-Purchase Parkway/KY 339 Wingo Exit 14 interchange starting on Monday, July 10, 2023.
The full closure of Purchase Parkway Wingo Exit 14 ramps is to allow reconstruction of the interchange to meet current interstate standards. The work is part of upgrades aimed at allowing Interstate 69 to be extended southward along the parkway from the 21 mile marker at Mayfield to the Kentucky-Tennessee State Line at Fulton.
Closure of all entry and exit ramps at Wingo Exit 14 will require motorists to detour via the KY 307 Fulton Exit 2 interchange or the U.S. 45/KY 80 Mayfield Exit 21 interchange to follow U.S. 45 to Wingo. Portable message boards will alert motorists to the ramp closures.
This extended ramp closure will also impact residents of the Clinton/Hickman County area who access the parkway via Exit 14. The closure of all ramps at Exit 14 is expected to be in place for up to 90 days or until approximately October 10, 2023.
Additionally, the contractor has northbound and southbound lane restrictions along the Purchase Parkway from the 13-mile marker to the 17.5-mile marker.
Motorists should be mindful of increasing construction activity along the Purchase Parkway extending northward from the Kentucky-Tennessee state line at Fulton (mile point 0.0) to the end of I-69 at the 21-mile marker near the U.S. 45/KY 80-Bypass at the southwest edge of Mayfield.
There is a 55 mph work zone speed limit with an enhanced police presence in areas where construction crews are present.
The two-year project includes converting the KY 339 Wingo Exit 14 interchange from a mini-cloverleaf originally designed to accommodate a toll booth to a modern modified-diamond interchange with extended ramps designed for high-speed interstate traffic.
The project will eventually include improvements to Exit 1 and Exit 2 at Fulton, bridge deck and barrier wall upgrades, as well as guardrail and drainage work all along the parkway from Fulton to Mayfield. On completion, the project will allow Interstate 69 to be extended along the final 21 miles of the existing parkway to the Kentucky-Tennessee State Line.
Along with ongoing construction to complete a new I-69 Ohio River crossing between Henderson and Evansville, Indiana, this project through parts of Graves, Hickman and Fulton counties is a significant step toward completing I-69 through Kentucky.
Jim Smith Contracting of Grand Rivers is the prime contractor on this $33.9 million project. The target completion date for all of the upgrades is December 15, 2024.
###
To get traffic advisories and alerts for KYTC District 1 counties via email please go to https://public.govdelivery.com/accounts/KYTC/signup/13651. Click on the District 1 counties you regularly drive through, or on any of the specialty corridors you travel. Check your SPAM filtering to assure Gov Delivery is on your approved list.